National Data Center Immersion Cooling Project Reaches 200 kW Demonstration Stage in Busan: Launch in June 2027
The consortium led by Samhwa Ace, working under the national project "Development and Demonstration of Ultra-Efficient Data Center Thermal Management Technology Using Immersion Cooling," presented Year-3 results and confirmed the Busan demonstration schedule at its second meeting (November 10, Korea Na Hotel, ~40 participants). Key parameters: 200 kW installation, 1,000 hours of operation in summer and winter, an absorption chiller driven by waste server water, and a target pPUE of 1.1. Installation at the LG CNS site is planned for March–April 2027, commissioning in May, and the main test in June.